In the past 12 months, we have successfully installed 15 Impressed Current Systems for our clients, bringing the total to over 50 systems installed in the last four years. The scope of work included the procurement and supply of essential materials, such as MMO anodes, Loresco backfill, and cables. Our services also encompassed drilling for anodes, creating cable trenches, and installing cables, test posts, and Transformer Rectifier units, culminating in thorough final commissioning to ensure optimal system performance.
location
South Australia
Metro, Regional and Remote
Total No. of Sites
15
Total Number of Anodes
190
Project Duration
6 Weeks
Type of Anodes
Mixed Metal Oxide
Backfill Type
Loresco SC3
Total length of Feeder Cable
>1500m
New TRUs
2