Pipe Line Digs on 8" Gas Main

  1. Home
  2. Project
  3. Pipeline Digs – 8″ Pipe

The scope of work encompassed various tasks, including site location, service identification, and weld identification, followed by mechanical excavation. We conducted the removal of existing coatings, abrasive blasting, and employed non-destructive testing (NDT) methods such as Magnetic Particle Inspection (MPI), Ultrasonic Testing (UT), as well as corrosion and mechanical damage measurements. After repairs, we ensured meticulous recoating, backfill, and reinstatement. The dig sites were located in the South East region of South Australia with dig sites located in road reserves, private lands and near other services. All digs were completed within 3 weeks and within budget, demonstrating our commitment to efficiency and quality.

project gallery

location

South East South Australia

Total No. of Digs

8

Total Length of Digs

50m

Project Duration

3 Weeks

Existing Coating

Yellow Jacket

New Coating

Denso Protal 7700

Anomalies

Corrosion and Bulge

Repairs

No repairs other than new coating